We close in two weeks and the radon test came back high. Is there time?

Direct answer

Usually yes, if scoping starts now. The install itself is a day; the verification retest needs 48 hours plus settling time. The sequence fits a two-week window when the first call happens early rather than after more negotiating.

More detail

Build the calendar backward. The closing needs a verification result in hand; the verification test runs at least 48 hours and starts after the system has run long enough to settle the house; the install takes a day; the scope visit and written quote come before that; and in Kentucky the tests on both ends of a transaction come from a certified measurement professional so nobody can challenge the numbers later. Laid end to end that is comfortably under two weeks, with margin for a stormy stretch that delays a test window. What burns the margin is the human part: days spent arguing over who pays before anyone schedules anything. The efficient move, whichever side you are on, is to get the fixed written quote immediately, because a real number converts an argument into a line item. Share the closing date, the foundation type, and the test report on the first call and the plan arrives built around the deadline. The who-pays FAQ and the real estate service page cover the negotiation side.

Authoritative sources

Ready to get started?

The inner Bluegrass sits on uranium-bearing limestone, and more than half of tested Fayette County homes have run elevated. Mon-Sat 8am-7pm.

Call (859) 780-8148Text us

Prefer to text? Open your texting app